Developers warn planning delays are restricting new housing supply
Industry submissions to the Victorian reform panel put the average assessment time for apartment projects at 14 months.
Submissions to the Victorian planning reform advisory panel published this week put the average assessment time for apartment projects above 50 dwellings at 14 months, roughly double the 2018 figure.
Developers identified referral authorities as the largest single contributor, accounting for about a third of elapsed time on a typical application. Several submissions proposed statutory response windows with deemed approval where the window lapses.
Councils, in their own submissions, pointed to under-resourcing and to applications lodged with incomplete documentation, which they said generated most requests for further information.
The panel is due to report in November. The state government has not committed to implementing its recommendations.
Sources
Related coverage
Infrastructure spending shifts to Melbourne's outer west
Transport investment is moving to the growth corridors where population is already arriving, reversing a decade of inner-city concentration.
Australia's apartment shortage is becoming a construction problem
Builders are declining work that would have been taken without hesitation five years ago. Fixed-price contracts, insolvency risk and a thin subcontractor market are converting a planning problem into a delivery problem.
Social housing delivery falls short of target in three states
Construction capacity, not funding, is the binding constraint on the current social housing programme.
Melbourne listings rise as spring selling season begins
Melbourne enters spring with the deepest pool of stock of any capital city. Agents report vendors are pricing to meet the market rather than testing it, keeping clearance rates stable even as choice widens.